EX0-008 · Question #5
A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis. What is the elapsed time required to complete the story?
The correct answer is B. 1.33 days. Elapsed time = ideal hours ÷ productive hours per day. With 8 ideal hours of work and only 6 productive hours available each day, the calculation is 8 ÷ 6 = 1.33 days, making B correct. Why the distractors are wrong: A (1.25 days) would require 8 ÷ 1.25 = 6.4 productive hours…
Question
A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis. What is the elapsed time required to complete the story?
Options
- A1.25 days
- B1.33 days
- C2 days
- DThis cannot be determined without knowing the velocity.
How the community answered
(37 responses)- A8% (3)
- B73% (27)
- C5% (2)
- D14% (5)
Explanation
Elapsed time = ideal hours ÷ productive hours per day. With 8 ideal hours of work and only 6 productive hours available each day, the calculation is 8 ÷ 6 = 1.33 days, making B correct.
Why the distractors are wrong:
- A (1.25 days) would require 8 ÷ 1.25 = 6.4 productive hours per day - a rate not given in the problem.
- C (2 days) is a common trap; it confuses "8-hour story in an 8-hour day = 1 day" intuition and then doubles it - there's no basis for that math here.
- D is wrong because velocity measures how many story points a team completes per sprint; it doesn't determine elapsed calendar time for a single story with known productivity data. You already have everything you need.
Memory tip: Think of it as a fuel economy problem - ideal hours is the distance, productive hours/day is your speed. Distance ÷ speed = time. Whenever a question gives you both "ideal effort" and "daily capacity," divide them directly; don't let the 8-hour workday distract you from the 6-hour productivity figure.