EXIN
EX0-002 · Question #9
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
The correct answer is D. Project Plan. See the full explanation below for the reasoning.
Question
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
Options
- AEnd Stage Report
- BTeam Plan
- CWork Package
- DProject Plan
How the community answered
(40 responses)- A8% (3)
- B18% (7)
- C5% (2)
- D70% (28)
Community Discussion
No community discussion yet for this question.