EXIN
EX0-002 · Question #77
EX0-002 Question #77: Real Exam Question with Answer & Explanation
The correct answer is D. Executive. See the full explanation below for the reasoning.
Question
Whose responsibility is it to assure the project's stakeholders that the project remains desirable, viable and achievable at all times?
Options
- AProject Manager
- BCorporate or programme management
- CSenior User
- DExecutive
Community Discussion
No community discussion yet for this question.