How is a Benefits Review Plan used in the Closing a Project process?

The correct answer is A. Checked for inclusion of activities to confirm those benefits which cannot be measured until after. See the full explanation below for the reasoning.

Question

How is a Benefits Review Plan used in the Closing a Project process?

Options

  • AChecked for inclusion of activities to confirm those benefits which cannot be measured until after
  • BTo capture the baseline measures against which to assess benefits
  • CTo capture side-effects (beneficial or adverse) identified during post-project benefits reviews
  • DTo gain approval for the post-project activities and transfer responsibility to corporate or

How the community answered

(31 responses)
  • A
    84% (26)
  • B
    3% (1)
  • C
    10% (3)
  • D
    3% (1)