EX0-002 · Question #53
EX0-002 Question #53: Real Exam Question with Answer & Explanation
The correct answer is D. Carrying out a risk response action to respond to a particular risk. See the full explanation below for the reasoning.
Question
Which statement describes the responsibilities of a risk actionee?
Options
- AIdentifying risks to the project that might occur in their department
- BOwning and authorizing the use of the risk budget to fund risk responses
- CManaging, monitoring and controlling of all aspects of an assigned risk
- DCarrying out a risk response action to respond to a particular risk