EX0-002 · Question #53

EX0-002 Question #53: Real Exam Question with Answer & Explanation

The correct answer is D. Carrying out a risk response action to respond to a particular risk. See the full explanation below for the reasoning.

Question

Which statement describes the responsibilities of a risk actionee?

Options

  • AIdentifying risks to the project that might occur in their department
  • BOwning and authorizing the use of the risk budget to fund risk responses
  • CManaging, monitoring and controlling of all aspects of an assigned risk
  • DCarrying out a risk response action to respond to a particular risk

Community Discussion

No community discussion yet for this question.