Why is the Initiating a Project process used?

The correct answer is B. To fully understand how the project objectives will be achieved before committing significant. See the full explanation below for the reasoning.

Question

Why is the Initiating a Project process used?

Options

  • ATo decide which project approach is suitable for the project
  • BTo fully understand how the project objectives will be achieved before committing significant
  • Cresources
  • DTo produce the required Work Packages
  • ETo enable corporate or programme management to give authorization to deliver a project

How the community answered

(46 responses)
  • A
    4% (2)
  • B
    72% (33)
  • C
    2% (1)
  • D
    13% (6)
  • E
    9% (4)

Community Discussion

No community discussion yet for this question.