What is the definition of a project outcome?

The correct answer is C. The result of the change derived from using the project's outputs. See the full explanation below for the reasoning.

Question

What is the definition of a project outcome?

Options

  • AA measurable improvement that is perceived as an advantage by one or more stakeholders
  • BThe reason for the project
  • CThe result of the change derived from using the project's outputs
  • DThe project's specialist products.

How the community answered

(37 responses)
  • A
    14% (5)
  • B
    3% (1)
  • C
    76% (28)
  • D
    8% (3)

Community Discussion