Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.

The correct answer is B. aim is to establish sound foundations to achieve a successful project. See the full explanation below for the reasoning.

Question

Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.

Options

  • Aminimum necessary is done to decide if a project is worthwhile
  • Baim is to establish sound foundations to achieve a successful project
  • CProject Brief is assembled and approved
  • Dproject approach appropriate for delivering a project is selected

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    81% (22)
  • C
    11% (3)
  • D
    4% (1)