EX0-002 · Question #33

Which statement about the Directing a Project process is FALSE?

The correct answer is C. Covers the day-to-day activities of the Project Manager. See the full explanation below for the reasoning.

Question

Which statement about the Directing a Project process is FALSE?

Options

  • ASupports the PRINCE2 principle of manage by exception
  • BIs triggered by a request to initiate a project
  • CCovers the day-to-day activities of the Project Manager
  • DProvides a mechanism for the Project Board to assure that there is continued business

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    11% (4)
  • C
    79% (30)
  • D
    3% (1)