EXIN
EX0-002 · Question #33
Which statement about the Directing a Project process is FALSE?
The correct answer is C. Covers the day-to-day activities of the Project Manager. See the full explanation below for the reasoning.
Question
Which statement about the Directing a Project process is FALSE?
Options
- ASupports the PRINCE2 principle of manage by exception
- BIs triggered by a request to initiate a project
- CCovers the day-to-day activities of the Project Manager
- DProvides a mechanism for the Project Board to assure that there is continued business
How the community answered
(38 responses)- A8% (3)
- B11% (4)
- C79% (30)
- D3% (1)
Community Discussion