EX0-002 · Question #28
Which PRINCE2 role has a specific responsibility for managing the information flows between the directing and delivering levels of the project?
The correct answer is A. Project Manager. See the full explanation below for the reasoning.
Question
Which PRINCE2 role has a specific responsibility for managing the information flows between the directing and delivering levels of the project?
Options
- AProject Manager
- BProject Support
- CTeam Manager
- DSenior User
How the community answered
(44 responses)- A75% (33)
- B7% (3)
- C16% (7)
- D2% (1)