EX0-002 · Question #28

EX0-002 Question #28: Real Exam Question with Answer & Explanation

Sign in or unlock EX0-002 to reveal the answer and full explanation for question #28. The question stem and answer options stay visible for context.

Question

Which PRINCE2 role has a specific responsibility for managing the information flows between the directing and delivering levels of the project?

Options

  • AProject Manager
  • BProject Support
  • CTeam Manager
  • DSenior User

Unlock EX0-002 to see the answer