EX0-002 · Question #21
Who is the key project decision-maker in the project management team?
The correct answer is B. Executive. See the full explanation below for the reasoning.
Question
Who is the key project decision-maker in the project management team?
Options
- ACorporate management
- BExecutive
- CChange Authority
- DProject Manager
How the community answered
(29 responses)- A3% (1)
- B72% (21)
- C7% (2)
- D17% (5)