EXIN
EX0-002 · Question #16
Which product identifies the management stages and timescales of a project?
The correct answer is C. Project Plan. See the full explanation below for the reasoning.
Question
Which product identifies the management stages and timescales of a project?
Options
- AProject Brief
- BProject Product Description
- CProject Plan
- DInitiation Stage Plan
How the community answered
(43 responses)- A14% (6)
- B5% (2)
- C79% (34)
- D2% (1)
Community Discussion