EX0-002 · Question #16

Which product identifies the management stages and timescales of a project?

The correct answer is C. Project Plan. See the full explanation below for the reasoning.

Question

Which product identifies the management stages and timescales of a project?

Options

  • AProject Brief
  • BProject Product Description
  • CProject Plan
  • DInitiation Stage Plan

How the community answered

(43 responses)
  • A
    14% (6)
  • B
    5% (2)
  • C
    79% (34)
  • D
    2% (1)