EX0-002 · Question #155
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
The correct answer is C. Corporate/programme management. See the full explanation below for the reasoning.
Question
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
Options
- ASenior User
- BExecutive
- CCorporate/programme management
- DSenior Supplier
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- C80% (20)
- D12% (3)