If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

The correct answer is C. Corporate/programme management. See the full explanation below for the reasoning.

Question

If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

Options

  • ASenior User
  • BExecutive
  • CCorporate/programme management
  • DSenior Supplier

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    80% (20)
  • D
    12% (3)