Who should act as the communication channel between a project and corporate or programme management?

The correct answer is A. Project Board. See the full explanation below for the reasoning.

Question

Who should act as the communication channel between a project and corporate or programme management?

Options

  • AProject Board
  • BProject Assurance
  • CProject Manager
  • DProject Support

How the community answered

(39 responses)
  • A
    74% (29)
  • B
    8% (3)
  • C
    15% (6)
  • D
    3% (1)