During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?
The correct answer is B. Business Case. See the full explanation below for the reasoning.
Question
During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?
Options
- AProject Product Description
- BBusiness Case
- CProject Brief
- DProject mandate
How the community answered
(47 responses)- A11% (5)
- B79% (37)
- C6% (3)
- D4% (2)