During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?

The correct answer is B. Business Case. See the full explanation below for the reasoning.

Question

During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?

Options

  • AProject Product Description
  • BBusiness Case
  • CProject Brief
  • DProject mandate

How the community answered

(47 responses)
  • A
    11% (5)
  • B
    79% (37)
  • C
    6% (3)
  • D
    4% (2)