Which task is performed by the Change Authority?

The correct answer is B. Approve or reject a request for change within approved limits. See the full explanation below for the reasoning.

Question

Which task is performed by the Change Authority?

Options

  • ASet a change budget
  • BApprove or reject a request for change within approved limits
  • CRefer changes that exceed budgetary limits to the Project Manager for approval
  • DUpdate the configuration management system when a change is approved

How the community answered

(18 responses)
  • A
    6% (1)
  • B
    83% (15)
  • C
    11% (2)