Which task is performed by the Change Authority?
The correct answer is B. Approve or reject a request for change within approved limits. See the full explanation below for the reasoning.
Question
Which task is performed by the Change Authority?
Options
- ASet a change budget
- BApprove or reject a request for change within approved limits
- CRefer changes that exceed budgetary limits to the Project Manager for approval
- DUpdate the configuration management system when a change is approved
How the community answered
(18 responses)- A6% (1)
- B83% (15)
- C11% (2)