EX0-002 · Question #123
Which part of the project management team is responsible for briefing corporate or programme management about project progress?
The correct answer is C. Project Board. See the full explanation below for the reasoning.
Question
Which part of the project management team is responsible for briefing corporate or programme management about project progress?
Options
- ATeam Manager
- BProject Support
- CProject Board
- DProject Manager
How the community answered
(58 responses)- A5% (3)
- B2% (1)
- C83% (48)
- D10% (6)