EX0-002 · Question #12
Which is a responsibility of the managing level within the project management team?
The correct answer is C. Ensure that the products are produced within the constraints agreed with the Project Board. See the full explanation below for the reasoning.
Question
Which is a responsibility of the managing level within the project management team?
Options
- ASet project tolerances
- BApprove stage completion
- CEnsure that the products are produced within the constraints agreed with the Project Board
- DAppoint the project management team
How the community answered
(38 responses)- A3% (1)
- B16% (6)
- C74% (28)
- D8% (3)