Which is a responsibility of the managing level within the project management team?

The correct answer is C. Ensure that the products are produced within the constraints agreed with the Project Board. See the full explanation below for the reasoning.

Question

Which is a responsibility of the managing level within the project management team?

Options

  • ASet project tolerances
  • BApprove stage completion
  • CEnsure that the products are produced within the constraints agreed with the Project Board
  • DAppoint the project management team

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    16% (6)
  • C
    74% (28)
  • D
    8% (3)