EX0-002 · Question #118
When are tolerances for a Work Package agreed?
The correct answer is A. When accepting a Work Package. See the full explanation below for the reasoning.
Question
When are tolerances for a Work Package agreed?
Options
- AWhen accepting a Work Package
- BAs work on each product within the Work Package begins
- COnce ail products have been developed and approved
- DWhen the Stage Plan is authorized by the Project Board
How the community answered
(34 responses)- A74% (25)
- B15% (5)
- C3% (1)
- D9% (3)