EX0-002 · Question #118

When are tolerances for a Work Package agreed?

The correct answer is A. When accepting a Work Package. See the full explanation below for the reasoning.

Question

When are tolerances for a Work Package agreed?

Options

  • AWhen accepting a Work Package
  • BAs work on each product within the Work Package begins
  • COnce ail products have been developed and approved
  • DWhen the Stage Plan is authorized by the Project Board

How the community answered

(34 responses)
  • A
    74% (25)
  • B
    15% (5)
  • C
    3% (1)
  • D
    9% (3)