Which describes the 'Identify Risks' step within the recommended risk management procedure?

The correct answer is D. Identify uncertainties that may impact on the delivery of the project objectives. See the full explanation below for the reasoning.

Question

Which describes the 'Identify Risks' step within the recommended risk management procedure?

Options

  • AIdentify responses to risks documented in the Business Case
  • BGather information about the project environment and objectives
  • CIdentify the roles to be involved in risk management activities
  • DIdentify uncertainties that may impact on the delivery of the project objectives

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    15% (5)
  • D
    76% (25)