EXIN
EX0-002 · Question #103
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
The correct answer is C. open issues and risks. See the full explanation below for the reasoning.
Question
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
Options
- Athe measurement of benefits NOT yet realized
- Bthe handover of products
- Copen issues and risks
- Dthe release of resources
How the community answered
(64 responses)- A5% (3)
- B9% (6)
- C70% (45)
- D16% (10)
Community Discussion
No community discussion yet for this question.