You are planning an SAP S/4HANA conversion. Which conversion-specific tasks need to be performed during the preparation phase?

The correct answer is C. Check the compatibility of custom code with SAP S/4HANA. Checking custom code compatibility (C) is a preparation phase task because it must happen before conversion begins - you need to identify which custom ABAP programs, function modules, or enhancements are incompatible with S/4HANA using tools like the Custom Code Migration app…

Pre-Checks and Planning

Question

You are planning an SAP S/4HANA conversion. Which conversion-specific tasks need to be performed during the preparation phase?

Options

  • APerform the migration of data to the new data structure.
  • BRun the database migration to the SAP HANA database.
  • CCheck the compatibility of custom code with SAP S/4HANA.
  • DSolve problems from the simplification item (SI) checks.

How the community answered

(59 responses)
  • B
    2% (1)
  • C
    95% (56)
  • D
    3% (2)

Explanation

Checking custom code compatibility (C) is a preparation phase task because it must happen before conversion begins - you need to identify which custom ABAP programs, function modules, or enhancements are incompatible with S/4HANA using tools like the Custom Code Migration app or SAP Readiness Check, so you can plan remediation work.

Why the distractors are wrong:

  • A (data migration to new structures) and B (database migration to SAP HANA) both occur during the technical conversion/realization phase - they are execution steps, not preparation steps.
  • D (solving SI problems) is a trap: while running simplification item checks is part of preparation, solving the identified problems spans the realization phase, making it not strictly a preparation-phase task.

Memory tip: Think of the preparation phase as "assess, don't act" - you're checking and analyzing (custom code compatibility, SI checks, system sizing), whereas actual migration of data and databases happens when the conversion executes.

Topics

#preparation phase#custom code compatibility#SI checks#data migration