E_S4CON_2505 · Question #2
What is the minimum SAP_BASIS release of an SAP ECC system that can be converted to an SAP S/4HANA Server?
The correct answer is B. 700. SAP ECC 6.0, which runs on SAP_BASIS 700 (SAP NetWeaver 7.0), is the oldest ECC version SAP officially supports as a source for System Conversion to S/4HANA. Because 700 is the baseline release for ECC 6.0, it becomes the floor for the conversion path - any ECC system at 700 or…
Question
What is the minimum SAP_BASIS release of an SAP ECC system that can be converted to an SAP S/4HANA Server?
Options
- A731
- B700
- C740
- D750
How the community answered
(50 responses)- A2% (1)
- B92% (46)
- C4% (2)
- D2% (1)
Explanation
SAP ECC 6.0, which runs on SAP_BASIS 700 (SAP NetWeaver 7.0), is the oldest ECC version SAP officially supports as a source for System Conversion to S/4HANA. Because 700 is the baseline release for ECC 6.0, it becomes the floor for the conversion path - any ECC system at 700 or higher is eligible.
Why the distractors are wrong:
- A (731) and C (740) and D (750) are all valid source releases for conversion, but they represent later Enhancement Packages or NetWeaver versions - none of them is the minimum. Choosing any of these confuses "a supported release" with "the lowest supported release."
Memory tip: Think "7-0-0 = Zero excuses" - SAP ECC 6.0 launched on BASIS 700, and SAP drew the conversion floor right there. If you remember that ECC 6.0 = BASIS 700, you'll always know the minimum.
Topics
Community Discussion
No community discussion yet for this question.