Which of the following milestones represent a DA project moving from Construction to Transition stage?

The correct answer is B. Sufficient functionality. See the full explanation below for the reasoning.

Question

Which of the following milestones represent a DA project moving from Construction to Transition stage?

Options

  • AProduction ready
  • BSufficient functionality
  • CProven architecture
  • DContinued viability
  • EStakeholder vision

How the community answered

(52 responses)
  • A
    8% (4)
  • B
    73% (38)
  • C
    2% (1)
  • D
    4% (2)
  • E
    13% (7)