Which of the following is a process goal in the Construction stage?

The correct answer is C. Prove architecture early. See the full explanation below for the reasoning.

Question

Which of the following is a process goal in the Construction stage?

Options

  • AExplore scope
  • BDevelop test strategy
  • CProve architecture early
  • DForm team
  • EEnsure production readiness

How the community answered

(57 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    84% (48)
  • D
    4% (2)
  • E
    9% (5)