DASSM · Question #40

True or False: A project that follows a Scrum or Agile life-cycle still needs the Inception, Construction or Transition phases.

The correct answer is A. True. See the full explanation below for the reasoning.

Question

True or False: A project that follows a Scrum or Agile life-cycle still needs the Inception, Construction or Transition phases.

Options

  • ATrue
  • BFalse

How the community answered

(20 responses)
  • A
    75% (15)
  • B
    25% (5)