DASSM · Question #21
A team has completed the work in their iteration backlog earlier than expected. There's still three days left of the iteration, what should the team do now?
The correct answer is D. Report the differences in completion time so the next iteration can be planned more efficiently.. See the full explanation below for the reasoning.
Question
A team has completed the work in their iteration backlog earlier than expected. There's still three days left of the iteration, what should the team do now?
Options
- AWork on noncritical tasks until the product owner can them more work.
- BWait for the other groups to complete their work prior to doing anything else.
- CWork with the product owner to pull more work from the product backlog into their iteration
- DReport the differences in completion time so the next iteration can be planned more efficiently.
How the community answered
(31 responses)- A3% (1)
- B16% (5)
- C6% (2)
- D74% (23)