If you can measure only one thing you should measure the cost of delay. This is reflected in which of the following principles of DA?
The correct answer is D. Optimize flow. See the full explanation below for the reasoning.
Question
If you can measure only one thing you should measure the cost of delay. This is reflected in which of the following principles of DA?
Options
- AKeep workloads within capacity
- BAccelerate value delivery
- CCollaborate proactively
- DOptimize flow
How the community answered
(66 responses)- A5% (3)
- B8% (5)
- C17% (11)
- D71% (47)