How should iterations for an agile project be planned?
The correct answer is A. At the beginning of each iteration by pulling from product backlog. See the full explanation below for the reasoning.
Question
How should iterations for an agile project be planned?
Options
- AAt the beginning of each iteration by pulling from product backlog.
- BIteratively by the product owner to ensure global optimization.
- CThroughout the project by using iteration reviews to continuously improve quality.
- DAt the retrospective meetings to ensure nothing is missed from one iteration to the next.
How the community answered
(25 responses)- A80% (20)
- B4% (1)
- C4% (1)
- D12% (3)