What is the primary risk addressed by the stakeholder vision milestone?
The correct answer is B. That your primary stakeholders agree to your strategy. See the full explanation below for the reasoning.
Question
What is the primary risk addressed by the stakeholder vision milestone?
Options
- AThat your architectural strategy is likely to work
- BThat your primary stakeholders agree to your strategy
- CThat the business case for the project is viable
- DThat a release plan for the project is realistic
How the community answered
(58 responses)- A9% (5)
- B72% (42)
- C3% (2)
- D16% (9)