CSSGB · Question #133
Basic tool of statistical process control. It consists of a run chart, together with statistically determined upper and lower control limits and a centerline.
The correct answer is A. Control Chart. Control Chart (A) is correct because it is precisely defined as a run chart augmented with a centerline (typically the process mean) and statistically derived upper and lower control limits (UCL/LCL), used to monitor whether a process is in statistical control over time. Confiden
Question
Basic tool of statistical process control. It consists of a run chart, together with statistically determined upper and lower control limits and a centerline.
Options
- AControl Chart
- BConfidence Interval
- CStatistical Control Process
- DControl Plan
How the community answered
(29 responses)- A93% (27)
- C3% (1)
- D3% (1)
Explanation
Control Chart (A) is correct because it is precisely defined as a run chart augmented with a centerline (typically the process mean) and statistically derived upper and lower control limits (UCL/LCL), used to monitor whether a process is in statistical control over time.
Confidence Interval (B) is a statistical range estimating where a population parameter lies - it's a standalone inferential statistic, not a process monitoring tool with control limits plotted over time. Statistical Control Process (C) reverses the actual term ("Statistical Process Control"), which is the broader methodology - the Control Chart is one tool within that methodology, not the methodology itself. Control Plan (D) is a quality document listing how to monitor and control process inputs/outputs, but it's a planning document, not a chart with plotted data and control limits.
Memory tip: Think "Control Chart = run chart with a fence" - the UCL and LCL are the fences that signal when a process has gone out of control, and the centerline is the path down the middle.