At the very initiation of a project a Belt must develop a concise _______________ that states at a high level the area of concern and why it is important this issue be improved.

The correct answer is C. Management Justification. See the full explanation below for the reasoning.

Define Phase

Question

At the very initiation of a project a Belt must develop a concise _______________ that states at a high level the area of concern and why it is important this issue be improved.

Options

  • ABusiness Case
  • BProject Doctrine
  • CManagement Justification
  • DProcess Owner Disclosure

How the community answered

(57 responses)
  • A
    5% (3)
  • B
    11% (6)
  • C
    82% (47)
  • D
    2% (1)

Topics

#project charter#business case#project initiation#problem statement