nerdexam
ASQ

CSSBB · Question #211

A project activity not on the critical path has required 20% longer than the time originally allocated. The project team should:

The correct answer is C. study the effect this will have on other activities because the project may still be on schedule. See the full explanation below for the reasoning.

Define Phase

Question

A project activity not on the critical path has required 20% longer than the time originally allocated. The project team should:

Options

  • Ainform all concerned that the entire project will be delayed by 20%
  • Binform all concerned that the entire project will be delayed but by less than 20%
  • Cstudy the effect this will have on other activities because the project may still be on schedule

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    14% (5)
  • C
    80% (28)

Topics

#critical path#project scheduling#float#project management

Community Discussion

No community discussion yet for this question.

Full CSSBB Practice