The primary metric for a project is reduced cost for process A .A consequential metric could be:
The correct answer is D. all the above. See the full explanation below for the reasoning.
Define Phase
Question
The primary metric for a project is reduced cost for process A .A consequential metric could be:
Options
- Areduced cycle time
- Breduced scrap rate
- Creduced set-up time
- Dall the above
- Enone of the above
How the community answered
(48 responses)- A2% (1)
- B4% (2)
- C2% (1)
- D83% (40)
- E8% (4)
Topics
#consequential metrics#primary metrics#project metrics#performance measurement