The primary metric for a project is reduced cost for process A . Baseline data might include:

The correct answer is A. current maintenance costs. See the full explanation below for the reasoning.

Measure Phase

Question

The primary metric for a project is reduced cost for process A . Baseline data might include:

Options

  • Acurrent maintenance costs
  • Bcurrent selling price for the products or services output by process A
  • Ccurrent suggestions from stakeholders of process A
  • Dall the above
  • Enone of the above