A team has been asked to reduce the cycle time for a process. The team decides to collect baseline data. It will do this by:
The correct answer is C. obtaining accurate cycle times for the process as it currently runs. See the full explanation below for the reasoning.
Measure Phase
Question
A team has been asked to reduce the cycle time for a process. The team decides to collect baseline data. It will do this by:
Options
- Aseeking ideas for improvement from all stakeholders
- Bresearching cycle times for similar processes within the organization
- Cobtaining accurate cycle times for the process as it currently runs
- Dbenchmarking similar processes outside the organization
How the community answered
(36 responses)- A3% (1)
- B6% (2)
- C81% (29)
- D11% (4)
Topics
#baseline data#cycle time#data collection#current state