A project whose definition does not include performance metrics:

The correct answer is D. should not be approved. See the full explanation below for the reasoning.

Define Phase

Question

A project whose definition does not include performance metrics:

Options

  • Awill typically be short term
  • Buse statistical inference
  • Chave a high risk of failure
  • Dshould not be approved
  • Enone of the above

How the community answered

(24 responses)
  • B
    4% (1)
  • C
    4% (1)
  • D
    79% (19)
  • E
    13% (3)

Topics

#project charter#performance metrics#project selection