CSM-001 · Question #97
Who determines whether the development team has been assigned enough work in a Sprint?
The correct answer is A. The Development Team. See the full explanation below for the reasoning.
Question
Who determines whether the development team has been assigned enough work in a Sprint?
Options
- AThe Development Team
- BThe Product Owner
- CThe Product Owner and the Scrum Master
- DThe Scrum Master
How the community answered
(19 responses)- A84% (16)
- C11% (2)
- D5% (1)
Community Discussion
No community discussion yet for this question.