The correct answer is A. The Development Team. See the full explanation below for the reasoning.

Question

Who determines whether the development team has been assigned enough work in a Sprint?

Options

  • AThe Development Team
  • BThe Product Owner
  • CThe Product Owner and the Scrum Master