________________ constitute the Sprint Backlog and are often estimated in hours?
The correct answer is D. Tasks. See the full explanation below for the reasoning.
Question
________________ constitute the Sprint Backlog and are often estimated in hours?
Options
- AUser Stories
- BUse Cases
- CFeatures
- DTasks
How the community answered
(52 responses)- A17% (9)
- B4% (2)
- C8% (4)
- D71% (37)