GAQM
CSM-001 · Question #83
What is the maximum amount of time that the team should spend in the daily scrum?
The correct answer is D. 15 minutes. See the full explanation below for the reasoning.
Question
What is the maximum amount of time that the team should spend in the daily scrum?
Options
- AAs long as it takes
- B1 hour
- C45 minutes
- D15 minutes
- E15 minutes, proportionally less for shorter Sprints
How the community answered
(30 responses)- B3% (1)
- C3% (1)
- D83% (25)
- E10% (3)
Community Discussion
No community discussion yet for this question.