The correct answer is E. All of the above. See the full explanation below for the reasoning.
Question
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
Options
- AMethods of communication
- BThe way the Scrum Team does Sprint Planning
- CSkills needed to improve the Development Team's ability to deliver
- DIts Definition of Done
- EAll of the above