CSM-001 · Question #73
What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity?
The correct answer is B. By facilitating Development Team decisions and removing impediments. See the full explanation below for the reasoning.
Question
What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity?
Options
- ABy ensuring the meetings start and end at the proper time
- BBy facilitating Development Team decisions and removing impediments
- CBy preventing changes to the Backlog once the Sprint begins
- DBy keeping high value features high in the Product Backlog
How the community answered
(49 responses)- A2% (1)
- B82% (40)
- C10% (5)
- D6% (3)