Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

The correct answer is C. The Development Team. See the full explanation below for the reasoning.

Question

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

Options

  • AThe Project Manager
  • BThe Scrum Team
  • CThe Development Team
  • DThe Product Owner

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    9% (3)
  • C
    82% (27)
  • D
    3% (1)