Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
The correct answer is C. The Development Team. See the full explanation below for the reasoning.
Question
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
Options
- AThe Project Manager
- BThe Scrum Team
- CThe Development Team
- DThe Product Owner
How the community answered
(33 responses)- A6% (2)
- B9% (3)
- C82% (27)
- D3% (1)