What is the Release Burndown?
The correct answer is B. A measure of the remaining Product Backlog across the time of a release plan. See the full explanation below for the reasoning.
Question
What is the Release Burndown?
Options
- AA graph indicating what has been completed by the Scrum Team
- BA measure of the remaining Product Backlog across the time of a release plan
- CWhat has been completed by the Scrum Team to date
- DThe work remaining to be completed by the Product Owner
How the community answered
(25 responses)- A4% (1)
- B72% (18)
- C8% (2)
- D16% (4)
Community Discussion