As the Sprint planning progresses, the workload has grown beyond the development team's capacity. Whichaction makes most sense for the Team?

The correct answer is B. Collaborate with the Product Owner and potentially remove or change items. See the full explanation below for the reasoning.

Question

As the Sprint planning progresses, the workload has grown beyond the development team's capacity. Whichaction makes most sense for the Team?

Options

  • AWork overtime for the Sprint
  • BCollaborate with the Product Owner and potentially remove or change items
  • CCancel the Sprint
  • DStar the Sprint and recruit additional team members

How the community answered

(53 responses)
  • A
    19% (10)
  • B
    70% (37)
  • C
    8% (4)
  • D
    4% (2)