Who has the authority to cancel a Sprint?

The correct answer is C. The Product Owner. See the full explanation below for the reasoning.

Question

Who has the authority to cancel a Sprint?

Options

  • AThe team members
  • BThe Scrum Master
  • CThe Product Owner
  • DThe Project Manager

How the community answered

(57 responses)
  • A
    7% (4)
  • B
    18% (10)
  • C
    72% (41)
  • D
    4% (2)