In an Agile environment, planning happens at which two levels? (Choose two.)

The correct answer is A. release planning C. sprint planning. See the full explanation below for the reasoning.

Question

In an Agile environment, planning happens at which two levels? (Choose two.)

Options

  • Arelease planning
  • Bbacklog planning
  • Csprint planning
  • Dproduct planning

How the community answered

(48 responses)
  • A
    81% (39)
  • B
    13% (6)
  • D
    6% (3)

Community Discussion

No community discussion yet for this question.