___________ can change the priority of items in the _________ backlog at any time.

The correct answer is C. The Product Owner(s); Product. See the full explanation below for the reasoning.

Question

___________ can change the priority of items in the _________ backlog at any time.

Options

  • AThe Product Owner(s); Sprint
  • BThe Team; Product
  • CThe Product Owner(s); Product
  • DThe Scrum Master; Sprint

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    81% (21)
  • D
    4% (1)