___________________is responsible for the Scrum process, facilitate the team and protect the team from outside noise.

The correct answer is A. Scrum Master. See the full explanation below for the reasoning.

Question

___________________is responsible for the Scrum process, facilitate the team and protect the team from outside noise.

Options

  • AScrum Master
  • BScrum Owner
  • CProduct Owner
  • DStakeholder

How the community answered

(43 responses)
  • A
    72% (31)
  • B
    7% (3)
  • C
    16% (7)
  • D
    5% (2)