Who is responsible for prioritizing the stories that will be included in the iteration?

The correct answer is C. Product Owner. See the full explanation below for the reasoning.

Question

Who is responsible for prioritizing the stories that will be included in the iteration?

Options

  • AScrum Master
  • BDeveloper
  • CProduct Owner
  • DTeam

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    5% (2)
  • C
    71% (27)
  • D
    16% (6)